Project Name
Bothwell Bank
Location
Bothwell
Client
Miller Homes
Key Works Delivered on Site
Structural Earthworks
Soil Modification
Mass Deep Soil Mixing Displacement Piling
Sheet Piling
Reinforced Earth Retaining Walls
Project Start Date & Duration
May 2018 for 20 weeks
Topsoil Strip Volume
30,800m3
Cut/fill Volume
52,100m3
Formation
15,000m3
Soil Mixing
3,600m3

We were employed by our client, Miller Homes, as the design & build contractor for the enabling works at their site at Bothwell Bank where they are building 105 new homes. Miller Homes approached us during the land purchase stage so that we could assist with abnormal costs and ultimately assist with the land deal.

Project challenges / GDL solutions

Project benefits for the client