Project Name
NMIS
Location
Renfrewshire
Client
University of Strathclyde
Main Contractor
Morrison Construction
Date / Duration
October 2020 / 12 wks
Key Works Delivered on Site
Bulk Earthworks
Soil Stabilisation
Mass Soil Mixing
Topsoil Strip Volume
7,550m3
Cut/fill Volume
11,600m3

We were employed by the main contractor, Morrison Construction to complete the enabling works contract to form stabilised piling mats and reduce external make-ups for the new National Manufacturing Institute Scotland (NMIS). This flagship development is located within the new Advanced Manufacturing Innovation District Scotland in the Renfrewshire campus of the University of Strathclyde.

Project challenges / GDL solutions

Project benefits for the client