Client
Bellway Homes
Key Works Delivered on Site
Earthworks
Soil Modification
Soil Stabilisation
Date / Duration
Ph1 - July 2019 /4 wks
Ph2 - June 2020 / 3wks
Cut/Fill Volume
Ph1 - 14,000m3
Ph2 - 10,450m3

Appointed by Bellway Homes to provide modified housing platforms to eliminate the need for piling and to treat on-site materials to provide a road capping replacement material.

Project challenges / GDL solutions

Project benefits for the client